Start with a defined test scope
Source-based explanationCummins describes load banks as controlled electrical loads used to exercise a power source, with test results documented in writing. That explains the value of a recorded load test, but does not supply a complete factory acceptance procedure. [1]
Use & limitsThe source is a service explanation, not a current NFPA standard or a project-specific FAT specification.
What to ask next
Editorial checklist
- Agree the load type, power factor, steps, duration, measured quantities and acceptance limits before manufacture.
- Require equipment identification, calibrated measurement records, deviations and witness signatures. Link the report to the delivered set’s model and serial number.
Do not substitute one load condition for another
Source-based explanationAGN 087 explains the kWe/kVA relationship; AGN 068 discusses motor-starting demands and generating-set response. These references show why the test conditions need to match the performance question. [2][3]
Use & limitsPassing one steady resistive-load test does not establish every power-factor or starting-load capability.
What to ask next
Editorial checklist
- State separately whether you need rated active output, reactive capability, load-step recovery or a specific motor-start demonstration.
- Ask which requirements the proposed factory test covers and which remain for calculation or site verification.
Plan the installed-system check separately
Source-based explanationOur recommended acceptance plan separates factory equipment evidence from checks after installation. Transfer-switch training provides background on one interface that a factory load test alone may not exercise. [4]
Use & limitsThe actual SAT procedure and applicable requirements must be agreed by the project’s responsible parties.
What to ask next
Editorial checklist
- Allocate checks of installed transfer controls, alarms, protection, fuel, cooling and operational sequences to named parties.
- Keep FAT, SAT and later maintenance records separate. Record unresolved defects, retest conditions and who can approve final acceptance.
Output, duty and site conditions
Model, components and delivery basis
Entity, documents and test scope
Clarify exceptions before comparing
Sources, dates and scope
4 references. Each record keeps its own review date. A manufacturer disclosure is not an independent test; a retrieval date is not a price-effective date. Hover, focus or tap a numbered reference to inspect its source.
- [1]Manufacturer service explanationwww.cummins.com
Cummins · Load Bank Performance Testing ↗
Use & limits
Service explanation, not a complete FAT procedure, SAT protocol or current NFPA standard.Load Bank Performance Testing, main text
Publication date not stated · Web edition; publication date not stated · Reviewed 2026-10-22View the recorded evidence
Load banks apply controlled electrical loads; Cummins describes resistive exercise and written performance records.
- [2]Alternator application notewww.stamford-avk.com
STAMFORD | AvK · AGN 087: Power Factor ↗
Use & limits
Actual load power factor is not fixed at 0.8; a unit conversion does not validate engine output or size a complete set.PDF p.1, Definitions; subsequent capability discussion
Publication date not stated · Issue C; date not established · Reviewed 2026-10-22View the recorded evidence
Power factor relates active kWe to apparent kVA. Conventional alternator ratings use 0.8 lagging power factor.
- [3]Alternator application notewww.stamford-avk.com
STAMFORD | AvK · AGN 068: Motor Starting and Generating Set Considerations ↗
Use & limits
Use with the offered alternator data and motor starting method; this note does not supply a universal generator sizing multiplier.PDF pp.1–3, A Motor Starting and Engine Considerations
Publication date not stated · Issue B; date not established · Reviewed 2026-10-22View the recorded evidence
Motor starting introduces inrush kVA and changing kW demand as the motor accelerates; alternator and engine response both matter.
- [4]Manufacturer training materialwww.cummins.com
Cummins · Transfer Switches Made Easy ↗
Use & limits
Historical North American training with UL context; not the current requirements for every destination market.Presentation: selecting transfer switches
Published 2019-11-20 · PowerHour · 20 November 2019 · Reviewed 2026-10-22View the recorded evidence
Training introduces transfer-switch selection and the interface between power sources and loads.